The end-to-end execution of the $49M+ USD Jamaica Kiln 5 Debottleneck Project and Stack Replacement in Caribbean Cement Plant to increase the cement production.
• Develop and manage end-to-end project master schedule using Microsoft Project and Oracle Primavera with WBS, baseline and resource assignment, for $49M+ USD industrial project, covering preliminary phases and critical shutdown to ensure 100% deadline compliance.
• Plan preliminary phases focusing on the pre-assembly of main equipment, including ducts, dust collector, stack, and coal dosing systems.
• Schedule and monitor critical shutdown of 55 days for the successful installation of ducts, dust collectors and stack.
• Generate S-curves, deviations analysis, corrective actions, an