Electrical and Instrumentation Site Engineer
Orascom Construction
Mar 2017 - May 2018 (1 year 3 months)
Project:
El-Burullus Combined Cycle 4800MW Power Plant
job responsibilities:
AIR INTAKE Raceways, Pulling Cables, Instruments Installation, Cables
Termination
IPB (ISO PHASE BUS-DUCT) Erection
Medium and High Power Transformers Installation
Medium Power Transformers Testing
Power Control Center Erection, Panels Installation and cables Termination
Communication Systems (Telephone, Data and Paging) Installation
Indoor and Outdoor Light Current Systems Installations and Testing
Fire alarm system Installation
Gas Turbine (SGT5-8000H) Erection
Instrumentations installation
Duct Bank and Manholes Installation