Khaled Abd El Aty

Khaled Abd El Aty

About

Detail

Project Manager
Cairo, Cairo Governorate, Egypt

Contact Khaled regarding: 
work
Full-time jobs

Timeline


work
Job
school
Education

Résumé


Jobs verified_user 0% verified
  • E
    Project Manager
    Energya El-Sewedy HELAL
    Jul 2017 - Current (9 years 4 months)
    Project Manager for Sonker 66/22 kV GIS Substation located in Egypt Ain El Sokhna Client : Sonker Company Consultant : EPS Supervision : EETC Canal Region Main Contractor : Energya El-Sewedy HELAL
  • alfanar
    Project Manager
    alfanar
    Jan 2015 - Jun 2017 (2 years 6 months)
    alfanar is a major player in electrical ,manufacturing & construction industry with Headquarter in Riyadh, Saudi Arabia, and branches in Dubai, Doha, Cairo, Damascus, Suzhou and Chennai; Businesses and services include: manufacturing, construction, building industry, real estate development, marine services, information technology and communication, industrial ventures and investments Manage all commercial and technical aspects for the execution and oversight of an engineer-procure-construct (EPC) contracts  Responsible for producing detailed Monthly construction reports for Client and my Top Management  Continuously Monitoring Project Budget, accurately forecasting the remaining cost to complete  Responsible for Invoice collection and C
  • alfanar
    Deputy Project Manager
    alfanar
    May 2012 - Jan 2015 (2 years 9 months)
    Reporting to Senior Project Manager  Managing group of Project Engineers and evaluating site daily and weekly reports  Manage all commercial and technical aspects for the execution and oversight of an engineer-procure-construct (EPC)  Arranging the Invoice with all supporting documents to be presented to the Client  Reviewing Project Schedule along with planning engineer before approving the same from Senior Project Manager  Approving Material and service Purchase requests in line with scope and Budget  Follow up Main Material Design , Manufacturing and delivery and conducting review meetings with suppliers  Conducting Design review meetings with Designer (Electrical, Mechanical and Civil) to insure smooth progress of project  Condu
  • alfanar
    Project Engineer
    alfanar
    Feb 2007 - Apr 2012 (5 years 3 months)
    Project/Co-ordinator Engineer EHV Substations. 1- Study of Project Scope of Work and Contract. 2- Updating Tender Project Time Schedule. 3- Gathering Design Inputs to initiate Design Stage. 4- Controlling the Base Design stage and follow up with the Consultant for the approval accordingly Go Ahead for Manufacturing can be given to main equipment and proceeding with Construction work. 5-Responsible for Interfacing during detail design stage between all equipment. 6- Preparing Weekly and monthly progress reports. 7-Design Review regular meetings. Show less
  • E
    Control Engineer
    Electro Hydraulic Automation
    Jan 2006 - Feb 2007 (1 year 2 months)
    Working in the industrial field updating old fashion machines by introducing new techniques of control for example speed control devices (inverters and PLC)
Education verified_user 0% verified
  • Ain Shams University
    bachelor, Bachelor’s Degree, Electrical Power and Machine Department, Very Good
    Ain Shams University
    Jan 2000 - Jan 2005 (5 years 1 month)
  • A
    bachelor, BS, Electrical Power and Machine Dept.